Magnox

Jan 2015 to Sep 2017, and Mar 2014 to Sep 2014
Sector:
Nuclear Decommissioning Handling Equipment.

(For use with radiological intermediate level wet waste – ILWW)
Overview:
Nuclear Decommissioning of Intermediate Level Waste at Dungeness and Bradwell using AutoDesk Inventor 3D for 3 projects.
1st: An Advanced Vacuum Drying Skid (AVDS) for removing moisture from radioactive waste containers.
2nd: A Resin Retrieval System using a pumping technology to fill waste containers, and,
3rd: A Wet Waste Transfer System using a vacuum technology to transfer between container types, and in 2014,
In 2014, worked to deliver the Process Definition & Plant Design for a £500k radioactive ‘Sludge Heel’ Retrieval system.
Dungeness 'A' plant
Resin retrieval system at top of resin tanks
AVDS - Advanced Vacuum Drying Skid plant room
Wet Waste Transfer System - Cylinder DCIC to cube DCIC
Sludge Heel retrieval process definition P&ID
Plant room equipment, pipe and cable layouts for a wet waste resin retrieval system (including a steel balcony 20m high) for intermediate level wastes (ILW) as shown below
Resin Retrieval system
As part of the Wet Waste Transfer System, a ‘first of a kind’ purge trolly for Hydrogen removal from DCICs was needed as shown in the image below.
Hydrogen Purge Trolley
Worked with:
Stakeholder needs, nuclear site licensing and safety case constraints.
Sub-Contractor management, and Construction Design Management (CDM) regulations.
Using AutoDesk Inventor 3D CAD to BIM level 2 and BS 8888 for concept and detail design.
Contributed to authoring the functional specifications, and conducting risk assessments.
Adhering to regulations compliances such as CE-Marking, ATEX, PSSR / PED, and ASME B31.3 piping standards.
Ensuring ‘Double Containment’ as needed, and participating in ‘Optioneering’ within the safety case constraints.
Full details of this role:
BRADWELL:- Authored the Work Specification (WS) docs for 2 key AVDS safety elements to satisfy Nuclear, Radiological + Environmental Safety Case Compliances:
1/ The shutdown systems during fire hazards & ventilation system failures: and
2/ HEPA filter change-overs.
 Hydrogen Purge Trolley layout design done in 3D on Autocad 2015, & created from just a process flow diagram specification to a point where all piece-parts were designed & procured (vacuum disk, brackets, seals etc), & document pack completed. This purge trolley was the ‘first of a kind’ for Magnox, & allowed the safe removal of hydrogen from wet waste containers prior to drying on the AVDS.


Authored a number of Trolley related documents including Operation + Maintenance Instructions, & build instructions for the sub-contractor.
 
 
Managed sub-contractor activities during manufacture of the first trolley, & also responsible for establishing what levels of regulatory compliances were required for this ‘first of a kind’ item – CE Marking / ATEX / PSSR / PUWER / etc. Trolley complied in Summer 2015 with Site Licensing & safety cases for handling / processing nuclear waste materials. 
Purge Trolley P&ID
Completed Purge Trolley, and 3D design counterpart
AVDS Plant room, and the N2 pipe route to the N2 tank slab. (CAD model superimposed over Google Satelite view.)
AVDS Skid, and also shows 2 pipe support columns
DUNGENESS:- 3D layout Design of the Dungeness (DNA) AVDS plant room & all piping + cabling using Inventor 2012 in accordance with Nuclear Site License & safety conditions. Pipe supports designed with plant Floor Load & strength calculations completed. Defined the level of pipe stress calculations required from the vendor (shown to be a minimal) for the DNA pipework based on the ASME B31.3 pipe standard.
Implemented both Autodesk Inventor 3D software & Autodesk 3D Design Review software at DNA for the AVDS project, thus enabling collaborative working with colleagues, vendors, & the Decommissioning Authorities. 
The move to 3D methods gave benefits of improved project understanding across the work group, reduced installation & project completion timescales – & costs – by approx. 3 months, & £400k, as well as the ability to inherit 3D CAD data from vendors, thus taking the company toward BIM level 2 – the minimum requirement for work in the public sector such as nuclear de-commissioning.
2 AVDS drying stations and fume extractor. 2 Pipe supports columns also visible.
Upon completion of AVDS work in Spring 2016, plant layout work began in 3D for the Dungeness Resin Retrieval equipment, based on a just a P&ID specification. The Resin Retrieval System consisted of a number of key elements as follows:-
 
  • An elaborate suction pump system with in-built sensors inherited from another site (Hinkley Point A – HPA)
  •  
  • A radiologically shielded 60 meter double contained hose route & associated pipe supports rated to carry 700Kg per meter,
 
 
 

 

  
  • A radiologically shielded batch tank & pumps assembly to establish accurate fill quantities for the waste container (a DCIC,)
  • A substantial frame structure (Sway Frame) to support approx 15 tonnes of shielded batch tank sub assembly,
  • The supernate return pump with in-built sensors from HPA & its 40 meter double contained shielded return hose, & finally
  • The control room layout & cable route trunking tray locations 
3D design of batch tank and manufacturing drg beneath
Pump Skid connected to Shielded hoses
Double skin batch tank, part installed.
Wet Waste Transfer System (WWTS) concept scheme - used in the procurement spec definition to the vendor.
Having established the overall 3D layout (using Inventor 2012) of the main system items & the initial 3D GA drawing for the items listed above, colleagues focused on the detail design of the batch tank assembly while I was responsible for delivering the detail design, manufacturing drawings, calculation approvals, & supporting documents (Functional specifications, bought item datasheets, etc) for the Sway Frame, & the 700Kg / mtr shielded transfer pipe supports to carry the concrete troughs & lead shielding.
From winter 2016 I started work on the Dungeness Sludge Retrieval System contributing significantly to the system performance requirements to fill waste containers (DCIC’s) with sludge using a vacuum process.
Was responsible for concept 3D design layout & functional specification for a wet waste transfer system to empty part filled waste containers directly in to containers on the AVDS dryer.
Other images associated with this role:
Drawing of the resin retreival route, with a focus on the pipeline sheilding.
Job Description
Batch Tank location as a 3D CAD layout
AVDS Skid
Sheilded hose channel - hose & sheilding not present.
Sheilded hose channel - hose & sheilding not present.
Scroll to Top